2001
Blank
2001
Blank
2001
Awarded a 5 years Maintenance Term Contract in Civil 
Engineering by Shell Eastern Petroleum Pte Ltd in Pulau  Bukom
2001
First job for JGC Singapore at Glaxo Smith Kline Pharmaceutical Complex for extension of PB1
2002
First time working in Exxon Mobil for JGC Singapore for a new warehouse at Shipyard Road 
2003
Fast track project directly for Exxon Mobil SPO yard  expansion in Jurong Island completed on time without  safety infringement 
2004
Ventured into Power Plant Construction by completing Civil Engineering and structural steel work in excess of 1000 tons at Power Seraya Phase II expansion for TOA  Corporation 
2005
Extended a further 5 years Maintenance Term Contract  in Civil Engineering for Shell Eastern Petroleum in Pulau  Bukom 
2006
Awarded Tank Storage Project-Civil Engineering  Construction package by Chiyoda Singapore, Phase  of Vopak Terminal in Banyan, Jurong Island 
2007
Constructed a 1200 workers Dormitory and startup lay  down area of 200, 000m2 for Shell’s Houdini Project in  MEG, Ayer Merbau 
2007
Awarded by Chiyoda Singapore to continue Phase 2 of Vopak Terminal
2007
First project in SRC-Clean Fuel Project Civil
Engineering Construction package by JGC Singapore
2008
Main Contractor for Houdini BOS Control Discharged Facilities directly for Shell Eastern Petrochemical
Complex 2008 Awarded by Chiyoda Singapore to continue Phase 3 of Vopak Terminal
2008
Implementation Contractor for Shell’s Houdini SBRM 
Project-24 months working in a live plant brownfield  environment
2009
Negotiated and was awarded as Main
Contractor for Shell Eastern Petrochemical Complex to perform conversion, alteration, addition and renovation work for Pulau Bukom  existing building facilities-working without interrupting existing staff and their operation inside the facilities
2009
Awarded by Shell Eastern Petroleum Ltd directly a new 
5 years Maintenance Term Contract in Civil Engineering  in Pulau Bukom
2009
Awarded by Chiyoda Singapore to continue Phase 4 & 5 of Vopak Terminal